Development phase roadmap

...

Color

Meaning

Estimated

Not estimated

Done / To Validate

Block to BK - PT/ES

Risks

  1. Opt-in and in-app implementation: The planned and executed hours for Opt-in and in-app features are already at 66 hours.

  2. Uncertainty with Ketchup solution: The project lacks a finalized solution for handling Ketchup. This uncertainty poses a risk as it may require additional time and effort to determine and implement an appropriate solution.

  3. Pending refinements for QR code free refill.

    1. Developing and integrating QR code functionality, particularly for controlling the free refill period, can pose technical challenges.

    2. The project may have dependencies on external factors such as third-party APIs or software libraries for QR code generation or time tracking. Any issues or delays with these dependencies can impact the project timeline and functionality.

Following the dates planned to have the specific features on Prod Environment:

Requirement

Due Date(Prod env)

BK - PT/ES launch

Highlight Current Day

May 9th

Customize Hero Component

May 23th / Jun 06th

Brand Icons Account Menu

May 23th

User Agreements v2

May 23th

Push Notification

May 29th

Add "bag with handles" on the cart

Jul 4th

Blocker

In-App message

Jun 27th

Add extra ketchup sache on the cart

Aug 01st

Blocker

Generate a QR code to free refil drink

Aug 01st

Blocker

SDK dynamic links

Aug 01st

Generate a QR code to curbside

Aug 01st

Plastic/Sugar taxes adjustments on the receipt

Aug 15th

Different product images to HD, MO and pub. letter

Sep 12th

UTM Amplitude

Done / To validate

Improve component of loyalty program

Aug 29th

...