Development phase roadmap
...
Color | Meaning | ||
---|---|---|---|
Estimated | Not estimated | Done / To Validate | |
Block to BK - PT/ES |
Risks
Opt-in and in-app implementation: The planned and executed hours for Opt-in and in-app features are already at 66 hours.
Uncertainty with Ketchup solution: The project lacks a finalized solution for handling Ketchup. This uncertainty poses a risk as it may require additional time and effort to determine and implement an appropriate solution.
Pending refinements for QR code free refill.
Developing and integrating QR code functionality, particularly for controlling the free refill period, can pose technical challenges.
The project may have dependencies on external factors such as third-party APIs or software libraries for QR code generation or time tracking. Any issues or delays with these dependencies can impact the project timeline and functionality.
Following the dates planned to have the specific features on Prod Environment:
Requirement | Due Date(Prod env) | BK - PT/ES launch |
---|---|---|
Highlight Current Day | May 9th | |
Customize Hero Component | May 23th / Jun 06th | |
Brand Icons Account Menu | May 23th | |
User Agreements v2 | May 23th | |
Push Notification | May 29th | |
Add "bag with handles" on the cart | Jul 4th | Blocker |
In-App message | Jun 27th | |
Add extra ketchup sache on the cart | Aug 01st | Blocker |
Generate a QR code to free refil drink | Aug 01st | Blocker |
SDK dynamic links | Aug 01st | |
Generate a QR code to curbside | Aug 01st | |
Plastic/Sugar taxes adjustments on the receipt | Aug 15th | |
Different product images to HD, MO and pub. letter | Sep 12th | |
UTM Amplitude | Done / To validate | |
Improve component of loyalty program | Aug 29th |
...