Milestones
Milestone | Name | Outcome | Work required | How to test | Owner | Status | ||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Scope defined | Scope of the project has been agreed between BK DE, Oracle and RBI |
|
| TBD |
| ||||||
2 | Test environment ready | A testing environment has been provided to Oracle for them to develop and test against |
|
| Valentina |
| ||||||
3 | Integration developed | Integration from Oracle POS to RBI Loyalty (via Loyalty Middleware) is developed and tested in Staging environments. |
|
| Valentina Silvia |
| ||||||
4 | Integration readiness (Staging) | The Oracle POS > RBI Loyalty integration has been thoroughly tested by the business in Staging and all identified issues have been fixed |
|
| Silvia BK DE: TBC |
| ||||||
5 | Production environment ready | The Loyalty Production environment has been configured and is ready for use |
|
| Valentina |
| ||||||
6 | Integration readiness (Production) | New version of Oracle POS (loyalty-enabled) is working in Production in at least one store. |
|
| Silvia BK DE: TBC |
|
Info |
---|
Note: going live with loyalty will happen on a different project because we need to coordinate Mobile ordering and In-store (Oracle and all of the Kiosk providers) |
Dependencies
Oracle can only set up the PLU’s (on the Lab) for the Loyalty rewards once the Loyalty program has been defined. Assumption that there will be no new offers associated to the Loyalty program
RBI can only set up rewards on Sanity once the PLU’s have been issued
In-restaurant loyalty (redeem reward and earn loyalty points) can be tested as soon as:
Oracle development is completed
The Production environment is ready
In-restaurant redemption of open offers can only be tested once development of P2.M2 is completed
Open Items
Involve AFL’s in the testing
Is there any training required? In which milestone(s)?
...