Milestones

Assumption that the Loyalty programme mechanics has been locked as part of Project 1. Define the Loyalty programme
Info
Warning

This page is no longer in use since rPOS was cancelled.

Milestones

Milestone

Name

Outcome

Work required

How to test

Owner

Status

1

Scope defined

Scope of the project has been agreed between BK DE and RBI

  • Write down and agree scope between the 2 parties

  • Written document outlining the scope of the project

Daniel

Status
colourBlue
titleIN PROGRESS

2

Test environment ready

A testing environment has been provided to rPOS Team for them to develop and test against

  • Set up Loyalty testing environment in Staging

  • Share credentials with rPOS Team

  • rPOS Team to confirm they can access and use the test environment

Valentina

Status
colourGreen
titleCOMPLETED

3

Integration developed

Integration from rPOS to RBI Loyalty (via Loyalty Middleware) is developed and tested in Staging environments.

  • rPOS to develop the integration

  • RBI to support with questions and issues that might arise during development

  • rPOS Team will have access to both Postman to make integration calls, and testing versions of the apps to test the effects of loyalty calls

Valentina

Silvia

Status
colourBlue
titleIN PROGRESS

4

Integration readiness (Staging)

The rPOS > RBI Loyalty integration has been thoroughly tested by the business in Staging and all identified issues have been fixed

  • Set up rewards in rPOS

  • Configure the equivalent rewards in Sanity

  • Test that the rewards are working in the RBI app

  • Test that the rewards are working in store (Lab)

  • All testing to be done in the BK DE POS Lab and RBI Staging

  • Selected BK DE people would be given access to the RBI app so that they can use offers and rewards from their devices

Silvia

BK DE: TBC

Status
titleNOT STARTED

5

Production environment ready

The Loyalty Production environment has been configured and is ready for use

  • Set up Loyalty environment in Production

  • Share credentials with rPOS Team (pending)

  • rPOS Team to confirm they can access and use the Production environment

Valentina

Status
colourBlue
titleIN PROGRESS

6

Integration readiness (Production)

New version of rPOS (loyalty-enabled) is working in Production in at least one store.

  • Migrate POS rewards from Lab to Production

  • Migrate Sanity rewards content from Staging to Production

  • rPOS to install the Loyalty-enabled version of their POS in at least one store

  • BK DE Ops to train store personnel & Toshiba on how to use loyalty on the POS

  • Selected BK DE people to be given access to Loyalty on the RBI app in Production

  • Test that the configured offers and rewards are working in the app and in-store

Silvia

BK DE: TBC

Status
titleNOT STARTED

Info

Note: going live with loyalty will happen on a different project because we need to coordinate Mobile ordering and In-store (Toshiba and all of the Kiosk providers) [insert link]

Dependencies

Same as documented for Project 3. Integrate Toshiba POS with Loyalty