Milestones
Assumption that the scope of the
Milestone | Name | Outcome | Work required | How to test | Owner | Status |
---|---|---|---|---|---|---|
1 | Scope defined | Scope of the project has been agreed between BK DE, Toshiba and RBI |
|
| Daniel | IN PROGRESS |
1 | Integration developed | Integration from Toshiba POS to RBI Loyalty (via Partner API) is developed and tested in Staging environments. |
|
| Valentina Silvia | |
Training provided | ||||||
2 | Integration tested | New version of Toshiba POS (loyalty-enabled) is working in Production in at least one store. |
|
| Silvia BK DE: TBC | Silvia BK DE: TBC |
Note: going live with loyalty will happen on a different project because we need to coordinate Mobile ordering and In-store (Toshiba and all of the Kiosk providers) [insert link]
Detailed activities
Note: we should involve AFL’s in the testing
Lock program mechanics
Testing in Staging/Lab
Set up offers and rewards in Toshiba
Configure the equivalent offers in Sanity
Test that the offers/rewards are working in the app
Test that the offers/rewards are working in store (Lab)
Testing in Production
Migrate POS offers/rewards from Lab to Production
Migrate Sanity offers/rewards content from Staging to Production
dependency
Test that the offers/rewards are working in the app (selected users)
Test that the offers/rewards are working in store (selected stores + users)