Timelines and status are being managed on this Monday board.
Milestones
Milestone | Name | Outcome | Work required | How to test | Owner | Status |
---|---|---|---|---|---|---|
1 | Scope defined | Scope of the project has been agreed between BK DE and RBI |
|
| Daniel | IN PROGRESS |
2 | Test environment ready | A testing environment has been provided to rPOS Team for them to develop and test against |
|
| Valentina | COMPLETED |
3 | Integration developed | Integration from rPOS to RBI Loyalty (via Loyalty Middleware) is developed and tested in Staging environments. |
|
| Valentina Silvia | IN PROGRESS |
4 | Integration readiness (Staging) | The rPOS > RBI Loyalty integration has been thoroughly tested by the business in Staging and all identified issues have been fixed |
|
| Silvia BK DE: TBC | NOT STARTED |
5 | Production environment ready | The Loyalty Production environment has been configured and is ready for use |
|
| Valentina | IN PROGRESS |
6 | Integration readiness (Production) | New version of rPOS (loyalty-enabled) is working in Production in at least one store. |
|
| Silvia BK DE: TBC | NOT STARTED |
Note: going live with loyalty will happen on a different project because we need to coordinate Mobile ordering and In-store (Toshiba and all of the Kiosk providers) [insert link]
Dependencies
Same as documented for Project 3. Integrate Toshiba POS with Loyalty