Proposed Project Structure

Proposed Project Structure

#

Project

Purpose

Definition of Done

#

Project

Purpose

Definition of Done

1

Oracle Integration Readiness

To ensure that all required software integrations are working as expected before initiating any rollouts.

  • In-store ordering test cases are passing in the BK UK Test Lab.

  • Loyalty integration test cases (including Pay at Counter) are passing in the BK UK Test Lab.

  • The test cases above include Oracle and Acrelec.

2

Oracle Rollout (TBC)

To replace NCR as the POS provider for BK UK, with like-for-like features compared to today.

  • All live stores that currently use NCR as their POS to be using Oracle.

  • All Acrelec kiosks that are currently integrated with Toshiba to be integrated with Oracle instead

Milestones

Ordering

Activity

Owner

ETA

Status

Status comments

Activity

Owner

ETA

Status

Status comments

1

Confirm final menu structure format

@Marrara, Jean

Jan 6th

DONE

Documentation here: Oracle POS - Configuration . Note that we might adjust the structure, but content is finalized.

2

Menu configured on Oracle POS

Alex B

[ ]

in progress

Following Oracle POS - Configuration documentation.

  • Items

  • Combos

  • Offers

  • Rewards

  • Modifiers

Jan 16, 2025 – Alex re-built menu in Dec using priceSeq 1 and 2 and defSeq 1.

  • Items – e.g. Whopper item

    • defSeq 1 (defSeq 2 still exists but it’s disabled)

    • priceSeq 1 for in-store and 2 for delivery

  • Combos – e.g. Whopper meal

    • 1 PLU per meal.

    • Combo has 3 groups - whopper, drink and side.

    • Sizing is attached to the drink and side.

  • Modifiers

    • No long use “No lettuce” modifier. Instead use “Lettuce” modifier and control amounts through text prefix.

    • E.g. “lettuce” PLU is associated to a lettuce class, which is a member of the condiment groups (e.g. Whopper build)

  • Offers – not started

  • Rewards – not started

3

Menu configured on Sanity on RBI Staging

Alex B

[ ]

NOT STARTED

Following Oracle POS - Configuration documentation.

  • Items

  • Combos

  • Offers

  • Rewards

  • Modifiers

4

Handle new Oracle menu structure

Khumbu & RBI

[ ]

In progress

PriceSeq 1 or 2, DefSeq = 1.

5

All ordering test cases passing for each item

Alex B & RBI

[ ]

NOT STARTED

 

6

Test full menu

Alex B

[ ]

NOT STARTED

 

Delivery

Work on this milestone requirsl the basic Oracle <> RBI integration is available in Staging. However, we don’t need the whole menu to be configured to test delivery assignment and status updates.

Activity

Owner

ETA

Status

Status comments

Activity

Owner

ETA

Status

Status comments

Configure one item in Oracle

Alex B

 

NOT STARTED

 

Configure one item in Sanity

Alex B

 

NOT STARTED

 

Run simple order injection test with all test cases passing (driver assigned, delivery status updates) in staging

Alex B & RBI

 

NOT STARTED

 

Run simple order injection test with all test cases passing (driver assigned, delivery status updates) in prod

Alex B & RBI

 

NOT STARTED

 

Related content

Proposed project structure
Proposed project structure
More like this
Oracle Rollout - Project Brief
Oracle Rollout - Project Brief
More like this
Oracle Rollout - Remaining Restaurants
Oracle Rollout - Remaining Restaurants
More like this
Project Brief - First 100 Restaurants
Project Brief - First 100 Restaurants
More like this
Oracle POS - Testing Plan
Oracle POS - Testing Plan
More like this
Oracle Project Plan Overview
Oracle Project Plan Overview
More like this